No | Nama Peserta | K | A | T | P | PT | HN | H | P | PK | Alasan |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | cv. tri prima mandiri - 02.334.691.9-811.000 | Rp. 1.760.307.000,00 |
Rp. 1.760.307.000,00 |
||||||||
2 | cv. buana sibela - 01.864.851.9-811.000 | Rp. 1.776.664.000,00 |
Rp. 1.776.664.000,00 |
Tidak Mencapai Nilai Passing Grade Kualifikasi (70) | |||||||
3 | CV.Kencana Bakti - 01.987.427.0-811.000 | Rp. 1.707.434.000,00 |
Rp. 1.707.434.000,00 |
Kualifikasi lama pengalaman Manager Proyek dan Surveyor yang diinput dalam tabel kualifikasi spse berbeda dengan yang dilampirkan dalam dokumen penawaran | |||||||
4 | CV. Tiga Putra Utama - 02.488.175.7-811.000 | Rp. 1.760.550.000,00 |
Rp. 1.760.550.000,00 |
TDAK MELAMPIRKAN TABEL SUMBER DAYA; TDK MELAMPIRKAN URAIAN ANALISA TEKNIS PEKERJAAN SEBAGAI KELENGKAPAN LAMPIRAN PENAWARAN YG DISYARATKAN DALAM DOKUMEN PENGADAAN. | |||||||
5 | CV. HARAPAN BARU - 02.041.073.4-811.000 | Rp. 1.685.670.000,00 |
Rp. 1.685.670.000,00 |
HASIL PERHITUNGAN URAIAN ANALISA TEKNIS PEKERJAAN GALIAN TANAH (MEKANIS), TIDAK SESUAI ATAU TIDAK TERCERMIN DALAM JADWAL WAKTU PELAKSANAAN DAN TABEL SUMBER DAYA | |||||||
6 | CV. SUBUR ABADI JAYA - 01.732.168.8-811.000 | Rp. 1.789.000.000,00 |
Rp. 1.789.000.000,00 |
- HASIL PERHITUNGAN URAIAN ANALISA TEKNIS UNTUK SEMUA ITEM PEKERJAAN, TIDAK SESUAI ATAU TIDAK TERCERMIN DALAM JADWAL WAKTU PELAKSANAAN - TABEL SUMBER DAYA MELAMPAUI JANGKA WAKTU PELAKSANAAN - DALAM URAIAN ANALISA TEKNIS DIURAIKAN WAKTU PELAKSANAAN PEKERJAAN TIANG PANCANG PONDASI BRONJONG SELAMA 60 HARI KALENDER, SECARA TEKNIS TDK DAPAT DILAKSANAKAN PEKERJAAN KARENA JADWAL WAKTU PELAKSANAAN PEKERJAAN KESELURUHAN DALAM DOKUMEN LELANG YAITU 60 (ENAM PULUH ) HARI KALENDER | |||||||
7 | CV. KALJOS PERDANA - 02.282.484.1-954.000 | |
|
||||||||
8 | NYIUR MAS - 01.732.258.7-811.000 | |
|
||||||||
9 | CV. KARYA DHELON - 02.014.699.9-814.000 | |
|
||||||||
10 | bangun kabo lestari - 31.692.442.2-724.000 | |
|
||||||||
11 | PT. SAGA MAKMUR SEJATI - 02.070.535.6-954.000 | |
|
||||||||
12 | EKI PUTRA PRATAMA - 02.041.245.8-811.000 | |
|
||||||||
13 | PT. Kaogesa Abadi - 70.190.869.1-816.000 | |
|
||||||||
14 | cv. sulawesi mega utama - 02.041.067.6-811.000 | |
|
||||||||
15 | citra tamalakindo - 03.235.063.9-811.000 | |
|
||||||||
16 | CV. ODE KARYA KONSTRUKSI - 31.666.759.1-811.000 | |
|
||||||||
17 | PT RANDY KARYA PERSADA - 75.996.228.5-811.000 | |
|
||||||||
18 | CV. KHARISMA ASIAH - 01.864.478.1-811.000 | |
|
||||||||
19 | CV. DALENDO BUMI SULTRA - 75.761.400.3-811.000 | |
|
||||||||
20 | CV. Anugrah Asiah Contraktor - 31.681.445.8-811.000 | |
|
||||||||
21 | PT. HARTAMA SAPUTRA - 02.678.995.8-811.000 | |
|
||||||||
22 | CV. ARDIAN RAYA - 02.946.326.2-811.000 | |
|
||||||||
23 | CV. AMI PRATAMA - 02.832.770.8-811.000 | |
|
||||||||
24 | CV. WIDYATAMA PUTRA - 02.946.018.5-811.000 | |
|
||||||||
25 | CV. BELA ANOA - 01.601.999.4-811.000 | |
|
||||||||
26 | CV. MENARA TEKNIK - 66.403.066.5-811.000 | |
|
||||||||
27 | CV. HASTA PERKASA - 01.864.485.6-811.000 | |
|
||||||||
28 | Igale Multi Prima - 02.678.750.7-811.000 | |
|
||||||||
29 | CV. LUCKY PERKASA - 75.123.573.0-804.000 | |
|
||||||||
30 | PT. TENGGARA INDAH PERMAI - 72.179.954.2-815.000 | |
|
||||||||
31 | CV. TRIGIL - 70.996.286.4-821.000 | |
|
||||||||
32 | IDEAS 03 ENGINEERING, cv - 03.218.816.1-722.000 | |
|
||||||||
33 | CV.BUKIT PELANGI - 02.374.663.9-728.000 | |
|
||||||||
34 | CV. BUANA UMAR - 02.828.621.9-722.000 | |
|
||||||||
35 | Axkes Karya Gemilang - 31.692.438.0-724.000 | |
|
- A Evaluasi Administrasi
- T Evaluasi Teknis
- ST Skor Teknis
- P Penawaran
- PT Penawaran Terkoreksi
- HN Hasil Negosiasi
- SH Skor Harga
- SA Skor Akhir
- K Evaluasi Kualifikasi
- SK Skor Kualifikasi
- SB Skor Pembuktian
- H Evaluasi Harga/Biaya
- P Pemenang
- PK Pemenang Berkontrak